AI Data Center

Status: in development

Giant H is developing an 80 MW AI data center on part of its 165,000 m² site in Daegot-myeon, Gimpo. The building covers about 16,500 m² over three levels, with eight 10 MW data halls designed for liquid-cooled AI racks. The project is in development; figures on this page describe current intent and will change as permitting, grid connection, and tenant agreements progress.

The data center at dusk seen from a hill, fog in the fields, the sea and Choji Bridge faint on the horizon under the setting sun

Why we are building it

AI needs power and cooling in places that most data centers were never built for.

Most data centers in Korea were designed for racks of 5 to 15 kW. The GPU systems that train and serve today's models draw 100 kW or more per rack and need liquid cooling, a dedicated high-voltage connection, and floors built for the weight. That capacity is scarce in the capital region, where the grid is congested and large new loads wait years. Giant H already owns the land, has room for its own 154 kV substation, and sits 40 km from central Seoul on established fibre routes. Building here turns a land holding into national infrastructure.

Why we are building it
DemandAI training and inference need 100 kW-class racks; few Korean sites can host them today
PowerThe capital region grid is congested; an owned site with space for a dedicated substation shortens the path to power
LatencyClose enough to Seoul for real-time inference, far enough out for land and power
Sovereign AIKorean AI labs, public bodies, and regulated industries need compute that stays in Korea
OwnershipNo land purchase or assembly; capital goes into power, cooling, and the building
The groupCompute for the AI R&D unit; waste heat for the complex; a public sports complex for the town

Key figures

Key figures
Total investmentapprox. KRW 1 trillion, three phases (planned)
IT capacity80 MW (planned)
Building footprintapprox. 16,500 m², approx. 5,000 pyeong, building only (planned)
Outside the buildingParking, 154 kV substation, generator yard, and sports complex are separate
Gross floor areaapprox. 49,500 m² over three levels (planned)
Buildingapprox. 200 m × 82 m, height approx. 24.5 m (planned)
Data halls8 halls of 10 MW, approx. 2,400 m² each (planned)
Racksapprox. 1,100, at 40–130 kW per rack (planned)
Utility intakeapprox. 110 MVA at 154 kV (planned)
Design PUE1.20–1.25 at full load (planned)
Site areaapprox. 165,000 m²

Location and access

Location diagram: the site in Daegot-myeon, Gimpo, about 20 km from Incheon International Airport and about 40 km from central Seoul The site, Daegot-myeon Gimpo Incheon Seoul Gangnam Incheon International Airport Han River approx. 20 km approx. 40 km
Location and access
LocationDaegot-myeon, Gimpo-si, Gyeonggi-do
Distance to central Seoulapprox. 40 km
Distance to Incheon International Airportapprox. 20 km
Distance to the seaapprox. 6 km inland from the strait at Choji Bridge, Ganghwa
Road accessDaegot-geomdan-ro, fronting the site
Regional linksLocal Route 356 and the Capital Region Second Ring Expressway within approx. 3 km

Site plan

Aerial rendering of the planned AI data center: a long three-level building with rooftop dry coolers, a substation yard, and the tidal flats beyond
Site plan — building, substation, generator yard, reserve
Site plan: the data center building, a 154 kV substation, a generator yard, parking, a reserve plot, the complex zone to the west and the road to the east AI data center approx. 16,500 m² footprint · 3 levels 154 kV substation Generator yard · 40 units, HVO-ready Daegot-geomdan-ro Parking Complex zone sports · gallery · open ground Reserve 0 30 m N

Level 1: power and plant

The ground floor carries everything the halls depend on. Eight electrical blocks, one per data hall, sit along the north side; pump rooms and heat exchangers sit behind them. A central core holds the lobby, the security and network operations centre, stairs, and freight lifts. Two meet-me rooms sit at opposite ends of the building so that each fibre route lands in a different room.

Level 1: power and plant
Electrical blocks8, each with MV switchgear, UPS, and Li-ion battery rooms
MechanicalPump rooms, plate heat exchangers, water treatment
NetworkTwo meet-me rooms, carrier-neutral
OperationsSecurity and network operations centre, lobby, offices
LogisticsLoading dock, staging, storage, workshop
Level 1: power and plant
Level 1 plan of the AI data center: eight electrical blocks, pump rooms, central core with security and lobby, two meet-me rooms, loading dock Electrical block 1–2 UPS · Li-ion · MV switchgear Pumps · heat exchangers water treatment Electrical block 3–4 UPS · Li-ion · MV switchgear Pumps · heat exchangers water treatment Electrical block 5–6 UPS · Li-ion · MV switchgear Pumps · heat exchangers water treatment Electrical block 7–8 UPS · Li-ion · MV switchgear Pumps · heat exchangers water treatment Core stairs · lifts Security and NOC Lobby MMR A MMR B Loading dock · staging · storage Tenant fit-out · workshop · offices Dock 0 30 m N

Levels 2 and 3: data halls

Each upper floor holds four 10 MW data halls around the core. Halls have no raised floor: coolant and cable run overhead, racks stand on the slab. A coolant distribution gallery runs along the north side so that maintenance never enters the white space.

Levels 2 and 3: data halls
Halls per floor4 × 10 MW, approx. 2,400 m² each
Rack layout7 rows of about 20 racks per hall
Rack density40–130 kW, liquid-cooled; air-cooled rows for networking and storage
Floor loadingapprox. 20 kN/m² in the halls (planned)
Floor to floor7.0 m
Levels 2 and 3: data halls
Typical data hall floor: four data halls of about 2,400 square metres, each with seven rows of liquid-cooled racks, a coolant distribution gallery along the north side and a central core Coolant distribution gallery — CDUs, secondary loop Service corridor Tenant rooms · spares · fibre risers Data hall A · 10 MW · about 140 racks Data hall B · 10 MW · about 140 racks Data hall C · 10 MW · about 140 racks Data hall D · 10 MW · about 140 racks Core stairs · lifts meeting rooms 0 30 m N

Roof: heat rejection

The roof is the cooling plant. About 300 dry-cooler fan modules reject heat from a warm-water loop; adiabatic assist runs only on the hottest days. A heat reuse exchanger at the centre sends low-grade heat to the wellness and greenhouse programs of the complex.

Roof: heat rejection
Heat rejectionapprox. 300 dry-cooler fan modules with adiabatic assist
Loop temperature30–40 °C supply
Heat reuseUp to 10 MW thermal to the complex (planned)
Roof: heat rejection
Roof plan: a grid of dry cooler fan modules and a central heat reuse exchanger Heat reuse exchanger Dry coolers with adiabatic assist · about 300 fan modules · warm-water loop 30–40 °C 0 30 m N

Section and elevations

Section — floor to floor 6.5 m and 7.0 m, no raised floor, overhead coolant and cable
Building section through three levels with roof plant and level marks Level 1 · power and plant Level 2 · data halls A–D Level 3 · data halls E–H Roof plant · dry coolers ±0.0 +6.5 +13.5 +20.5 +24.5
South elevation — vertical louvers, one orange parapet line
South elevation Entrance 200 m +24.5
East elevation
East elevation 82 m +24.5

Power

Power
Grid154 kV, two incoming circuits on separate routes; connection study with KEPCO in preparation
SubstationOn-site 154/22.9 kV, three 60 MVA transformers, N+1 (planned)
Distribution22.9 kV ring, one electrical block per data hall
UPSLi-ion, 2N per hall, approx. 5 minutes at full load
Backup generation40 × 2.8 MW generators, HVO-ready, N+1 per block, 48 h fuel on site (planned)
RenewablesPower purchase agreements and renewable certificates, aiming to match 100% of load by Phase 3

Cooling

Cooling
PrimaryDirect-to-chip liquid cooling through CDUs, one per row
SecondaryRear-door heat exchangers for air-cooled racks, up to 30% of load
Free coolingMost hours of the year, given Gimpo's mild climate (planned)
WaterClosed loop; water use effectiveness below 0.2 L/kWh (target)
Heat reuseWarm water to the bath house, greenhouse, and site heating

Connectivity

Connectivity
FibreTwo diverse routes from Daegot-geomdan-ro, each into its own meet-me room
CarriersCarrier-neutral; all three national carriers invited (target)
LatencyRound trip to central Seoul under 1 ms (estimate)
Cloud accessPrivate on-ramps to major cloud regions in the Seoul area (planned)

Security and operations

Security and operations
PerimeterFive layers from site fence to rack, with vehicle barriers and mantraps
AccessBadge and biometric, escorted for visitors, logged per hall
Monitoring24/7 security and network operations centre on site
StandardsDesigned to Uptime Institute Tier III; ISO 27001, ISO 50001, and K-ISMS (targets)

Equipment

What goes inside, from the substation to the rack.

Liquid-cooled GPU rack with coolant manifolds

AI compute racks

The halls are built around liquid-cooled GPU racks of the NVL72 class: 72 GPUs in a single cabinet, cooled by cold plates on the chips and fed by a busbar. Lower-density rows hold networking, storage, and air-cooled servers.

AI compute racks
Rack positionsapprox. 1,100 across eight halls (planned)
High densityapprox. 560 racks at 120–130 kW, direct-to-chip liquid cooling
Standardapprox. 540 racks at 15–40 kW for network, storage, and CPU
Cabinet48U, up to 1,500 kg, rear coolant manifold
Supplied byTenants; the building provides power, cooling, and space
Coolant distribution unit with plate heat exchanger and pumps

Coolant distribution units

CDUs separate the clean coolant that touches the servers from the building water loop. Each serves a row of racks through a plate heat exchanger, redundant pumps, and fine filtration.

Coolant distribution units
Unitsapprox. 64, eight per hall, N+1 (planned)
Capacityapprox. 1.5 MW each
Supply30–40 °C to the racks
FluidTreated water with inhibitor, closed loop
Rows of dry coolers on the data center roof

Dry coolers

Heat from the halls leaves the building on the roof. Dry coolers blow outside air across finned coils; adiabatic pads pre-cool the air only on the hottest days, so the plant uses almost no water.

Dry coolers
Fan modulesapprox. 300 on the roof (planned)
Heat rejectionapprox. 100 MW thermal at full load
Water useAdiabatic assist only; WUE below 0.2 L/kWh (target)
Heat reuseUp to 10 MW thermal to the aquatic centre and site heating
154 kV power transformer in the substation yard

Substation and transformers

Power arrives at 154 kV on two circuits and is stepped down on site. Three main transformers are sized so that any one can be out of service without reducing capacity.

Substation and transformers
Intake154 kV, two incoming circuits on separate routes
Transformers3 × 60 MVA, 154/22.9 kV, N+1 (planned)
Switchyard154 kV gas-insulated switchgear
UtilityConnection study with KEPCO in preparation
Medium-voltage switchgear and UPS with lithium-ion batteries

Medium-voltage switchgear and UPS

Inside, a 22.9 kV ring feeds eight electrical blocks, one per hall. Each hall has two independent UPS paths on lithium iron phosphate batteries, bridging the seconds between a grid fault and the generators taking load.

Medium-voltage switchgear and UPS
Distribution22.9 kV ring, gas-insulated switchgear
UPS1.25 MW modules, approx. 128 in total, 2N per hall (planned)
BatteriesLithium iron phosphate, approx. 5 minutes at full load
MonitoringElectrical power monitoring down to each rack
Row of standby generator sets in the generator yard

Standby generators

If the grid fails, generators start within seconds and carry the whole campus. They run on renewable diesel (HVO) and are tested monthly.

Standby generators
Units40 × 2.8 MW, N+1 per block (planned)
FuelHVO-ready, 48 hours on site
EmissionsSelective catalytic reduction, acoustic enclosures
TestingMonthly load tests, annual full-campus test
Carrier-neutral meet-me room with fibre patch panels

Meet-me rooms

Carriers and cloud on-ramps meet tenants in two rooms at opposite ends of the building, each fed by its own fibre route, so that no single cut isolates the campus.

Meet-me rooms
Rooms2, carrier-neutral, approx. 40 cabinets each (planned)
FibreTwo diverse routes, separate building entries
CarriersAll three national carriers invited (target)
ServicesCross-connects, cloud on-ramps, dark fibre to Seoul
Security and network operations centre

Operations centre

One room watches everything: power, cooling, security, and network, twenty-four hours a day, with its own backup power and a view of every camera on site.

Operations centre
Staffing24/7, on site
SystemsBuilding management, power monitoring, DCIM, access control, video
ResponseEngineers on site at all hours; spares held on the campus
Mantrap booths at the secure entrance

Physical security

Access narrows in five steps from the site fence to the rack. Mantraps allow one person at a time, and every hall door is logged.

Physical security
LayersFence, gatehouse, building, hall, cage or rack
AccessBadge plus biometric; visitors escorted
VehiclesCrash-rated barriers at the gate
StandardsUptime Institute Tier III design; ISO 27001 and K-ISMS (targets)

Investment

A project of about KRW 1 trillion, built in three phases.

The figure covers the building, power, cooling, network, the sports complex, and the costs of getting to power. It excludes the land, which Giant H already owns, and the GPU hardware, which tenants bring.

By category

Investment by category
Building and civil worksKRW 200 billion
Electrical: substation, MV, UPS, generatorsKRW 330 billion
Mechanical: liquid cooling, heat rejection, heat reuseKRW 190 billion
Network, security, controlsKRW 60 billion
Sports complex and landscapeKRW 70 billion
Design, permits, grid contribution, contingencyKRW 150 billion
Totalapprox. KRW 1 trillion (planned)

By phase

Investment by phase
Phase 1 · 20 MWapprox. KRW 420 billion, including the substation and shared plant
Phase 2 · 40 MWapprox. KRW 230 billion
Phase 3 · 80 MWapprox. KRW 250 billion
Sports complexapprox. KRW 70 billion, alongside Phases 1 and 2
Contingencyapprox. KRW 30 billion

Phasing

  1. Phase 1 — Substation, Level 1 plant for blocks 1–2, data halls A and B: 20 MW.
  2. Phase 2 — Data halls C and D on Level 2: 40 MW.
  3. Phase 3 — Level 3, data halls E to H: 80 MW.

Tenancy and investment

Tenancy and investment
ModelWholesale halls of 10 MW, build-to-suit, or powered shell
TenantsAI cloud providers, hyperscalers, and domestic AI labs
TermLong-term leases, typically 10–15 years (planned)
ReturnsLease income per MW of IT load; long terms with inflation-linked escalation (planned)

Views

Not only a data center

Most data centers are fenced boxes at the edge of an industrial park: no reason to visit, nothing around them. This one sits on land we own, with the rest of the site planned for the people who live and work nearby. The halls are quiet by design. The land around them does not have to be.

Concept visualization of a running track, open field, and a low gallery pavilion beside the data center
Aquatic centre with a 25 m pool and a geothermal spa pool
How this site differs
Typical siteLeased land in an industrial park, fenced, no public program
This siteOwned land in open countryside, with a sports complex, a gallery, and open ground
Typical neighborA wall and a guard house
This neighborA running track on weekends, a cafe on the road, a gallery screening the films made on the campus's compute
Typical scheduleHalls first, everything else never
This scheduleOpen ground with Phase 1, sports and gallery with Phase 2, wellness after the geothermal study

Programs around the halls

Programs around the halls
Sports complex400 m track, multi-purpose field, indoor arena; public on weekends (planned)
GalleryContemporary and media art, with a screening room for AI R&D (planned)
WellnessBath house and spa on geothermal water reported at approx. 500 m depth (under study)
StayA small hotel for tenants, partners, and weekend guests (planned)
Open groundPaths, lawn, and planting along the field edges; opens with Phase 1 (planned)
  1. Phase 1 — Open ground
  2. Phase 2 — Sports complex, gallery
  3. After the geothermal study — Wellness, stay